GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects April 2023 – West Lake STEM

April, 2023 by Granite School District Communications Office

West Lake STEM Junior High School
Building Construction

Masonry walls for band, choral, and the auditorium are 95% complete.

Masons are placing veneer brick at exterior walls in the mechanical/cafeteria wing.

Structural steel placement in the administrative area is nearly complete.Roof decking is 65% in place. Once the roof is in place, drywall installation will begin in the two south wings.

Metal stud framing, plumbing, electrical, and mechanical systems are nearly complete on the first floor in the south wings of the academic building.




South academics wing.



Brick veneer facing.



HVAC systems.



Main office structural steel.