Cyprus High School
Building Construction
Auditorium roofing, steel in ceilings and back of house 2nd and 3rd floor continues.
Gymnasium and locker rooms have drywall being installed on one side of metal studs.
Electrical, fire sprinkler/alarm and plumbing continues in the locker rooms and gymnasium.
Gymnasium masonry on stairway walls and under the dance room as well as moving up to pool loft and locker rooms.
Pool roof decking installed, and roofing started. Observation upper deck installed.
Tilt walls for choral and band area have been stood. Steel moving to choral area soon.
![Band and choral walls in place](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-46.png)
![Auditorium steel](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-47.png)
![HVAC ducting over gymnasium](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-48.png)
![Framing and spray foam insulation](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-49.png)
![Last section of track being placed](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-50.png)
![Drywall on one side of metal studs in locker room/changing rooms](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-51.png)
![Masonry below dance room](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-52.png)
![Ducting to air handlers](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-53.png)
![Pool upper observation area decking installed](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-54.png)
![Pool trusses installed](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-55.png)
![Site overview](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-45.png)