West Lake STEM Junior High School
Building Construction
Band and choral room masonry walls are 90% complete and were scheduled to top out the week of January 30th upon which masons will move to auditorium area.
Contractor is placing decking for second floor in northwest academic wing and preparing to place roof decking on southeast academic wing.
Metal stud, framing, interior, plumbing, electrical, lighting, power, and mechanical system installation continues in south wings.
![Southwest academic wing exterior sheathing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-33.png)
![Gymnasium roof decking](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-34.png)
![Southeast academic steel trusses](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-35.png)
![Southeast academic framing 1st floor](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-36.png)
![Site overview auditorium and administration walls started](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-32.png)