GSD Future

Long-Term Capital Outlook and Planning

  • Home
  • 2017 Bond Info
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Copyright 2023
Granite School District

Status of Projects February 2023 – West Lake STEM

February, 2023 by Matthew Sampson

West Lake STEM Junior High School
Building Construction

Band and choral room masonry walls are 90% complete and were scheduled to top out the week of January 30th upon which masons will move to auditorium area.
Contractor is placing decking for second floor in northwest academic wing and preparing to place roof decking on southeast academic wing.
Metal stud, framing, interior, plumbing, electrical, lighting, power, and mechanical system installation continues in south wings.

Southwest academic wing exterior sheathing
Southwest academic wing exterior sheathing
Gymnasium roof decking
Gymnasium roof decking
Southeast academic steel trusses
Southeast academic steel trusses
Southeast academic framing 1st floor
Southeast academic framing 1st floor
Site overview auditorium and administration walls started
Site overview auditorium and administration walls started

Filed Under: Project Updates, West Lake

 