West Lake STEM Junior High School
Building Construction
Gymnasium roof trusses and 90% of roof decking is in place.
Locker room masonry walls 90% complete.
Kitchen and mechanical rooms masonry walls 50% complete.
Southwest academic wing framing is complete, exterior sheathing is 75% first floor utilities are 50% complete.
Southeast academic wing second floor decking and teacher hub/commons area concrete slab ready to be placed.
![Masonry for kitchen and mechanical rooms](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-10.png)
![Gymnasium steel roofing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-11.png)
![Commons area near teacher’s hub](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-12.png)
![Academic building and gymnasium](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-13.png)
![Southwest academic wing utilities and framing](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/03/image-9.png)