Cyprus High School
Building Construction
Tilt panels for gymnasium have been cast in concrete.
Pool foundation walls are complete.
Other foundation walls are being formed now and waiting for reinforcing steel.
Auditorium and stage walls have been formed, scheduled to pour 6/6/22
Underground electrical in kitchen area is being installed for transformers and generators.
All casting slabs for tilt walls are in place.
Crane and crane paths are in place, in preparation for standing tilt walls which is expected to begin late June.
![Cyprus Campus](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-130-300x170.png)
![Electrical conduits from transformers/generators](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-131-300x225.png)
![Fire hydrant in mechanical yard](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-132-300x225.png)
![Casting slab for tilt panels](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-133-300x225.png)
![Athletics and pool panels being prepped](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-134-300x169.png)
![Mockup panel](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-135-300x169.png)
![Preparation for tilt panels](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-136-300x225.png)
![Preparation for tilt panels](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-137-300x225.png)
![Main underground electrical](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-138-300x168.png)
![Geothermal drilling, 80 holes have been drilled](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-139-300x169.png)
![Swimming pool area](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2022/11/image-140-300x169.png)