Project Status Timeline

December, 2018 by Granite School District Communications Office

Here you can view the current status of all major capital projects in Granite School District, including completed work, current projects, and future construction dates.

SchoolProjectStatus
Valley Jr. HighMajor RemodelIn Use; Full Completion December 2018
Evergreen Jr. HighMajor RemodelIn Use; Full Completion December 2018
Granite Technical Institute5th Floor ExpanisionIn Use; Full Completion December 2018
Olene Walker ElementaryRebuild of Roosevelt ElementaryConstruction Complete Fall 2020
South Kearns ElementaryRebuildConstruction Complete Fall 2020
Hunter High SchoolWing AdditionConstruction Set to Complete 2021
Rosecrest ElementaryMajor RemodelIn Use; Completed 2019
Howard Driggs ElementaryMajor RemodelIn Use; Completed 2019
Cyprus High SchoolRebuildConstruction Begins 2020
Skyline High SchoolRebuildConstruction Begins 2020
West Kearns ElementaryRebuildArchitectural Design Work; Construction Scheduled to Begin 2020
Calvin Smith ElementaryMajor RemodelConstruction Scheduled to Begin 2021
Plymouth ElementaryMajor RemodelConstruction Scheduled to Begin 2021
Moss ElementaryMajor RemodelConstruction Scheduled to Begin 2021
Arcadia ElementaryRebuildConstruction Scheduled to Begin 2022
Taylorsville High SchoolWing AdditionConstruction Scheduled to Begin 2022
Orchard ElementaryRebuildConstruction Scheduled to Begin 2023
Kennedy Jr. HighMajor RemodelConstruction Scheduled to Begin 2023
Hillsdale ElementaryMajor RemodelConstruction Scheduled to Begin 2023
Academy Park ElementaryRebuildConstruction Scheduled to Begin 2024
Kearns Jr. HighRebuildConstruction Scheduled to Begin 2024
Magna ElementaryMajor RemodelConstruction Scheduled to Begin 2024
Valley Crest ElementaryMajor RemodelConstruction Scheduled to Begin 2024
Sandburg ElementaryRebuildConstruction Scheduled to Begin 2025
Pioneer ElementaryMajor RemodelConstruction Scheduled to Begin 2025
Lincoln ElementaryMajor RemodelConstruction Scheduled to Begin 2025
Eastwood ElementaryRebuildConstruction Scheduled to Begin 2026
Crestview ElementaryMajor RemodelConstruction Scheduled to Begin 2026
Spring Lane ElementaryRebuildConstruction Scheduled to Begin 2027
Cottonwood ElementaryMajor RemodelConstruction Scheduled to Begin 2027
Oakridge ElementaryRebuildConstruction Scheduled to Begin 2028
Valley Jr. HighRebuildConstruction Scheduled to Begin 2028
Evergreen Jr. HighRebuildConstruction Scheduled to Begin 2028

Filed Under: Project Updates