Rebuilds and Remodels are based on a ‘worst first’ timeline. Rebuild dates specify when construction is anticipated to begin. Our desire is to complete all necessary projects as soon as possible; however, this timeline is based on design work which is different for each type of school, and ensuring cash flow for all projects.
- A High School takes 18-24 months to design and roughly 2-3 years to construct.
- A Junior High School takes 18 months to design and 18-20 months to construct.
- An Elementary takes 10-12 months to design and 12-15 months to construct.
This phase is part of a 30-40 year strategic plan to rebuild and renovate all schools.