Updates:
Academics
● LVT flooring nearing completion on the Main Level
● Pre-cast stairs installed on Main Staircase
● Site concrete in Courtyard being poured
● Student/teacher furniture being delivered and installed
● Ceiling tile dropped in all corridors
● Tile nearing completion throughout building
● All teacher material has been removed from the old Academics building and is being stored/moved into the new building
● Abatement of old building started June 3rd
● Casework nearing completion throughout all classrooms
● Manufacturing lab equipment being set
● Kitchen equipment installed