  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

Status of Projects June 2024 – Cyprus High School

June 2024

Updates:

Site Work:
● Stadium field base
● Stadium field fencing
● Stadium field drainage
● Flatwork behind home bleachers

Athletics/Pool:
● Track glass handrail
● Precast concrete benches in team locker rooms
● Pool plumbing

Administration/Commons:
● Framing in Administration
● Curtain wall/glazing around the Commons
● Testing Center siding

Academics/CTE:
● Finish paint, casework, and ceiling in Level 3 Academics
● Ceiling grid Levels 2 and 3 Academics
● Underground plumbing/electrical Manufacturing Shop

Performing Arts:
● Auditorium clouds finished

Recent Photos:

Stadium field base and perimeter fencing
Stadium field base and perimeter fencing
Stadium field drainage and curbing
Stadium field drainage and curbing
Flatwork behind the home team bleachers
Flatwork behind the home team bleachers
Glass handrail in Athletics
Glass handrail in Athletics
Pre-cast benches in team locker rooms
Pre-cast benches in team locker rooms
In-ground plumbing progress in the Pool
In-ground plumbing progress in the Pool
Framing in Administration
Framing in Administration
Glass glazing and frames outside Commons Area
Glass glazing and frames outside Commons Area
Testing Center siding
Testing Center siding
Casework, ceiling grid, and paint in Academics
Casework, ceiling grid, and paint in Academics

Filed Under: Cyprus

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2025 Granite School District

 

Loading Comments...