Updates:
- The three Academic wings are having countertops installed on cabinets, sinks installed in the restrooms, and wiring and sensors placed in the ceilings.
- The Administration wing has cabinets ready to be installed.
- The Serving area has decorative wall tile being installed.
- HVAC ducts are 90% complete.
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/03/West-Lake-9.jpg)