Academics
●High ceiling in Cafeteria painted
●Exterior glass complete at Main Entrance
●Metal wood look soffits near completion in Cafeteria
●Storefront glass frames installed at Media Center
●Interior glass in classroom groups started
●Carpet and electrical trim started in Level 2 general classrooms
●Cabinet installation ongoing in Level 3 Science classrooms
●Painting on Level 2 near completion
●Main Corridor tile complete on Levels 2 and 3
●Tile at the Smoothie Bar complete
●Plumbing fixtures set in Administration Suite bathrooms