Updates:
Site Work:
- Underground utility work nearing completion in the central courtyard
Academics:
- Cafeteria steel complete minus the activity stairs
- Glass on main Academics Building 90 percent complete
- Roof completed on the entire building
- Final paint started in the Administration Suite
- Athletics Vestibule life safety is complete, finishes (tile, paint, flooring) starting soon
- Drywall ongoing on all floors, 90 percent complete on the second floor
- In wall electrical, plumbing nearing completion on all floors
- Steel at the south stair tower nearing completion
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-1.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-2.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-3.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-4.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-5.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-6.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-7.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-8.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-9.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-10.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Skyline-11.png)