Updates:
Site Work:
● Asphalt paved on the North end of the site
● Asphalt prep for the Southwest parking lot
● Outbuildings concrete floors poured
Athletics:
● Basketball standards installed
● Tile in the PE locker rooms
Pool:
● Locker room framing and plumbing
CTE Buildings:
● Tilt panels stood into place
Administration:
● Framing drywall throughout classroom spaces
Social Studies:
● Exterior glass installed
● Exterior framing
Cafeteria/Common Area:
● Level 3 concrete floor poured
● Exterior framing
Performing Arts:
● HVAC in corridors and Scenery/shop storage
● Glass installation in the Choral and Band room
Recent Photos:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-1.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-2.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-3.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-4.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-5.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-6.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-7.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-8.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-9.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-10.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-11.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-12.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-13.png)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2023/11/Cyprus-14.png)