Updates:
Building Exterior:
● Glass installation at the Auditorium
● Glass installation at Academics
Athletics/Pool:
● Pool excavation/footings
● Tile in Pool locker rooms
● Ceiling tile in Athletics Vestibule
● Tectum panels in Weight Room
Administration/Commons:
● Slab on grade in Cafeteria Area of Commons
● Level 1 framing and HVAC in Administration
● Level 2 and 3 framing
Academics/Social Studies:
● Framing Level 2
● Framing and electrical Level 3
Performing Arts:
● Drywall on the Proscenium
● Paint and framing in Scenery Shop
Recent Photos:
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C1.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C2.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C3.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C4.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C5.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C6.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C7.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C8.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C9.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C10.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C11.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C12.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C13.jpg)
![](http://cdn-5b8b6132f911c804dc845e9d.closte.com/wp-content/uploads/2024/04/C14.jpg)