Objective
Update the GSD Board and Superintendency on the progress of major construction projects overseen by the Architecture, Engineering & Construction Department on behalf of Granite School District.
Security Upgrades
Security Remodels – New Projects
Plan review 11/09/2021
- Hartvigsen School
- Rolling Meadows Elementary
- William Penn Elementary
- Oakwood Elementary
- Woodstock Elementary

OakridgeElementary – Security Remodel / Addition
- Completion projected for mid November.
- Exterior concrete work and paving are complete.
- Retaining walls are in place and ready for landscaping to begin.
- Elevator is installed and being prepared for certification.
- Interior framing is complete.
- Drywall installation is on going, to be followed by tile installation.
Oakridge Elevator Addition



Infrastructure Replacement
Cottonwood High School – Track Reconstruction
- Final walk through was 11/02/2021.
- Track is complete and being used by the students and community.
- North and South side fencing are installed.
Cottonwood Track


New Construction
Skyline High School – Athletics Complex
- Mechanical, electrical and plumbing are ongoing
- Interior painting and locker room tile are underway.
- Retaining walls and perimeter fencing to begin early November.
- Demolition contractor will mobilize mid November for woodshop / arts building and cafeteria.
Skyline Campus & Pool


- Skyline High School Cost Summary
- Construction Management Fees – PO #070055
- Construction Payments to Date: $3,495,226.82
- Change Orders Requiring Board Authorization Owner Request
- CO1 Increase Project Cost: $3,649,771.00
- Change Order Sub Total: #3,649,771.00
- Phase 1 – Baseball Field – PO #070441
- Construction Payments to Date: $3,211,958.50
- Advancing Work Into Earlier Phase
- CO1 Temporary Parking: $208,891.99
- Unknown Conditions
- CO2 Various Changes: $60,139.64
- Staff Level Change Orders: -$266,179.97
- Change Order Sub Total: $2,851.66
- Phase Advancement Sub Total: $208,891.99
- Phase 2 – Athletics – PO #170038
- Construction Payments to Date: $29,814,746.15
- Change Orders Requiring Board Authorization Owner Request
- CO2 Relo T&M June ’20: $299,956.75
- CO3 Relo T&M July’20: $310,642.14
- CO7 Snowmelt System: $111,226.20
- CO8 Relo T&M Oct – Nov ’20: $351,866.78
- CO10 Modular Kitchen: $137,500.00
- CO14 Baseball Contingency Rollover: $62,984.00
- CO20 Relo T&M Feb – March ’21: $116,227.43
- CO21 Portable Electric One Line Diagram: $168,883.32
- CO24 Portable Mechanical / Electrical Work Scope: $349,556.65
- CO26 Relo T&M April – May ’21: $90,494.79
- CO30 Relo T&M June ’21: $99,184.55
- CO32 Temporary Utilities / Relo T&M July – Aug ’21: $270,934.30
- Advancing Work Into Earlier Phase
- CO12 Field Rough In / Site Lighting: $78,896.51
- CO30 Remporary Steam Piping: $575,357.20
- Unknown Conditions
- CO@& Football Stadium Soils: $107,237.02
- Errors & Omission
- CO23 Structural Review / Toilet Stall Revisions: $203,420.76
- Staff Level Change Orders: -$2,767,813.53
- Change Order Sub Total: $566,554.87
- Phase Advancement Sub Total: $654,253.71
- Phase 3 – Site Package – PO #270113
- Construction Payments to Date: $2,061,85.78
- Advancing Work Into Earlier Phase
- CO2 Temporary Parking Lot: $193,225.74
- Staff Level Change Orders: -$1,580,827.79
- Change Order Sub Total: -$1,387,602.05
- Phase Advancement Sub Total: $193,225.74
- Summary
- Payments to Date – Grand Total: $38,583,717.25
- Change Order – Grand Total: $2831,575.48
- Phase Advancement – Grand Total: $1,056,371.44
- Bid Price: $168,726,996.00
- Revised Cot: $171,558,571.48
- Construction Management Fees – PO #070055
Cyprus High School – Building Construction
- Groundbreaking ceremony was held 11/01/2021.
- Contractors are preparing footings, starting in the gymnasium, locker rooms, and swimming pool.
- Underground plumbing is progressing for the gymnasium locker rooms.
Cyprus Building Construction


- Cyprus High School Cost Summary
- Phase1 Mass Grading – PO #170253
- Construction Payments: $4,170,965.69
- Change Orders Requiring Board Authorization Owner Request
- CO2 Ames 2-1 Slopes 23,444CY: $167,624.60
- Staff Level Change Orders: $116,091.09
- Change Order Sub Total: $283,715.69
- Phase 2 Construction – PO #270185
- Construction Payments toDate: $1,510,585.96
- Change Orders Requiring Board Authorization Owner Request
- CO1 VE contract research & clarifications revision: $117,489.00
- Change Order Sub Total: $117,489.00
- Summary
- Payments to Date – Grand Total: $5,681,551.65
- Change Order – Grand Total: $401,204.69
- Bid Price: $169,871,606.00
- Revised Cost: $170,272,810.69
- Phase1 Mass Grading – PO #170253
West Lake STEM J unior High School – Demolition / Site Preperation
- The demolition of the building is done
- Soils are being imported, compacted and site is being staged for construction.
- Soil compaction testing is being conducted and all tests so far have passed inspection.
West Lake Demolition




- West Lake STEM Junior High School Cost Summary
- Phae 1 Demolition and Abatement – PO #270183
- Demolition Payments to Date: $577,166.04
- Change Order Sub Total: $0.00
- Symmary
- Payments to Date – Grand Total: $577,166.04
- Change Order – Grand Total: $0.00
- Bid Price For Demolition and Abatement Revised Cost: $1,238,846.00
West Lake STEM Junior High School – Replacement
- Project is in design.
- 90% plan review was held on 12//03/2021.
- Request for Proposal has been issued fo contractors for pre-qualification.
- Bid release 11/29/2021.