Status of Projects
December 2021
Architecture, Engineering & Construction

December, 2021 by Granite School District Communications Office

Objective

Update the GSD Board and Superintendency on the progress of major construction projects overseen by the Architecture, Engineering & Construction Department on behalf of Granite School District.

Security Upgrades

Security Remodels: New Projects

Hartvigsen School and Rolling Meadows Elementary plans are under review.

Expected to go out to bid in January.

Security Upgrades Timeline
Security Upgrades Timeline

Oakridge Elementary: Security Remodel / Addition

Interior tile work continues moving on to upper level.

Store front is installed at the first floor level. Glass installation starts 12/06/21.

Store front installation for upper level is delayed due to shipping issues. State elevator inspection is scheduled for 12/21/21.

Oakridge Elevator Addition
Oakridge Elevator Addition
Oakridge Elevator Addition
Oakridge Elevator Addition
Oakridge Elevator Addition
Oakridge Elevator Addition

New Construction

West Lake STEM Junior High School: School Design

West Lake Junior Community Council reviewed the new school floor plan, elevations and color schemes. The exterior colors were sent out to the community at large for feedback.

Pre-bid meeting was 12/01/21.

Mountain Red / Pearl Taupe was the
top choice with 51% of the votes.
Mountain Red / Pearl Taupe was the top choice with 51% of the votes.
Platinum / Cimarron was the second
choice with 31% of the votes.
Platinum / Cimarron was the second choice with 31% of the votes.
Ochre Buff / Colonial Tan was the
third
choice with 17% of the votes.
Ochre Buff / Colonial Tan was the third choice with 17% of the votes.

Skyline High School: Athletics Complex

Pool excavation complete.

Kitchen and cafeteria demolished.

Mount Olympus sewer main work at north property line has started.

Electrical work at north pedestrian walkway is progressing.

The tilt panel casting slab at the softball complex has been placed.

Earth work at demolished art building in progress.

Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Skyline Campus Construction
Shared north drive verti-block retaining wall \ Hughes General Contractors
Demolition of arts building
Pool lobby storefront
Locker room tiling
  • Skyline High School Cost Summary
    • Construction Management Fees / PO #070055
      • Construction Payments to Date: $3,633,371.60
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing work into earlier phase
      • Unknown Conditions
      • Errors & Omission
      • Staff Level Changer Orders
      • Change Order Sub Total: $5,827,842.00
    • Phase 1 – Baseball Field / PO #070441
      • Construction Payments to Date: $3,211,958.50
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing work into earlier phase
      • Unknown Conditions
      • Errors & Omission
      • Staff Level Changer Orders: -$266,179.97
      • Change Order Sub Total: $2,841.66
      • Phase Advancement Sub Total: $208,891.99
    • Phase 2 – Athletics / PO #170038
      • Construction Payments to Date: $3,563,439.40
      • Change Orders Requiring Board Authorization Owner Request
        • CO34 Temp T&M Aug/Sept: $76,658.24
        • CO34 Temp T&M Sept/Oct: $67,519.28
      • Advancing work into earlier phase
      • Unknown Conditions
      • Errors & Omission
      • Staff Level Changer Orders: -$2,732,763.93
      • Change Order Sub Total: $745,781.99
      • Phase Advancement Sub Total: $654,253.71
    • Phase 3 – Site Package / PO #270113
      • Construction Payments to Date: $2,293,680.78
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing work into earlier phase
      • Unknown Conditions
        • CO3 Sewer Line Revisions / Softball Field Water Line: $70,910.42
      • Errors & Omission
      • Staff Level Changer Orders: -$1,580,827.79
      • Change Order Sub Total: -$1,316,691.63
      • Phase Advancement Sub Total: $193,225.74
    • Phase 4 – Academic Building / PO #270306
      • Construction Payments to Date
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing work into earlier phase
      • Unknown Conditions
      • Errors & Omission
      • Staff Level Changer Orders: -$2,178,071.00
      • Change Order Sub Total
      • Phase Advancement Sub Total
    • Summary
      • Payments to Date – Grand Total: $40,702,450.28
      • Change Order – Grand Total: $5,259,784.02
      • Phase Advancement – Grand Total: $1,056,371.44
      • Bid Price: $168,726,996.00
      • Revised Cost / Does not include CO 34 & 35 or CO 3: $171,593,621.08

Cyrus High School: Builing Construction

Continuing underground plumbing for gymnasium and locker rooms.

Gymnasium and locker rooms rebar is being installed and concrete footings are being poured.

The New Cyprus High School

Project timeline infographic, details below
  • Project Timeline
    • 11/04 – Submittal List Returned to Architect with Requested Revisions Incorporated
    • 11/19 – First Pour of Concrete Footings
    • 11/22 – U/G Sewer Utility Work Started
    • 11/29 – Building Site Preparation Continues
    • 11/29 – U/G MEP Installation Continues
    • 11/29 – Geothermal Drilling Work Planned to Begin, pending materials procurement
  • Manpower Onsite
    • Snapshot from Total = Westland (4), Suntec (5), KSC (6), US Mech (8), CR Lighting (4)
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Constructionf
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
Cyprus Building Gymnasium Construction
The New Cyprus High School  - Progress Photos
The New Cyprus High School – Progress Photos
The New Cyprus High School  - Progress Photos
The New Cyprus High School – Progress Photos
The New Cyprus High School - Lookahead Schedule
The New Cyprus High School – Lookahead Schedule
The New Cyprus High School - Lookahead Schedule
The New Cyprus High School – Lookahead Schedule
  • Cyprus High School Cost Summary
    • Phase 1 Mass Grading / PO #170253
      • Construction Payments: $4,170,965.69
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing Work Into Earlier Phase
      • Unknown Coditions
      • Errors & Omission
      • Staff Level Change Orders: $116,091.09
      • Change Order Sub Total: $283,715.69
      • Phase Advancement Sub Total
    • Phase 2 Construction / PO #270185
      • Construction Payments to Date: $3,031,541.48
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing Work into Earlier Phase
      • Unknown Conditions
      • Errors & Omission
      • Staff level Change Orders: $1,734.02
      • Change Order Sub Total: $119,223.02
      • Phase Advancement Sub Total
    • Summary
      • Payments to Date – Grand Total: $7,202,507.17
      • Change Order – Grand Total: $520,763.82
      • Phase Advancement – Grand Total
      • Bid Price: $169,871,606.00
      • Revised Cost: $170,274,544.71

Filed Under: Project Updates