• Skip to primary navigation
  • Skip to secondary navigation
  • Skip to main content
  • Skip to primary sidebar

Granite School DistrictGranite School District logo

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact
  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates

West Lake STEM Jr. High Safety Tour – August 2024

August 2024

Filed Under: Project Updates, West Lake

Cyprus High Construction Tour – August 2024

August 2024

Filed Under: Cyprus, Project Updates

Status of Projects June 2024 – West Lake STEM

August 2024

Updates:

  • Administrative staff has moved in.
  • Furniture and appliance delivery continues.
  • We are moving in and setting up classrooms.

Recent Pictures:

Hardwood floor in Dance Room installed
Hardwood floor in Dance Room installed
Hardwood floor in Gymnasium progressing
Hardwood floor in Gymnasium progressing
Floor slab preparation for tile in Tech Lab
Floor slab preparation for tile in Tech Lab
Hexagon ceiling cloud tiles in Main Corridor
Hexagon ceiling cloud tiles in Main Corridor
Kitchen equipment installation
Kitchen equipment installation
Kitchen equipment installation
Kitchen equipment installation
Preparation of planting areas on east and north of the building
Preparation of planting areas on east and north of the building
Preparation of planting areas on east and north of the building
Preparation of planting areas on east and north of the building
Landscaping on south side of campus
Landscaping on south side of campus
Landscaping on south side of campus
Landscaping on south side of campus

Filed Under: West Lake

Status of Projects August 2024 – Skyline High School

August 2024

Updates:

Academics
●ACM metal panels completed on exterior
●Student desks and chairs installed in all general classrooms
●Classroom moveable partitions nearing completion
●Flooring complete throughout building
●Final kitchen equipment being set
●Wall graphics in building completed
●All building furniture has been moved into the building
●Teacher pallets have been moved into the building
●Classroom AV equipment nearing completion
●Classroom relocatables complete in west parking lot
●Demolition of old Academics building about 50% complete

Recent Pictures:

Graphic in Hallway leading to Athletics Building
Graphic in Hallway leading to Athletics Building
Main Entrance with metal panels complete
Main Entrance with metal panels complete
World map graphic in Counseling reception area
World map graphic in Counseling reception area
Special Education classroom progress
Special Education classroom progress
Sewing lab classroom nearing completion
Sewing lab classroom nearing completion
Teacher equipment installation in Ceramics
Teacher equipment installation in Ceramics
Teacher’s Lounge near Administration Suite
Teacher’s Lounge near Administration Suite
Finishes in Level 2 corridor
Finishes in Level 2 corridor
Relocatables set in west parking lot
Relocatables set in west parking lot
Serving line equipment being set
Serving line equipment being set
Demolition of old Academics building
Demolition of old Academics building
Teacher collaboration near Level 2 Media Center
Teacher collaboration near Level 2 Media Center

Filed Under: Skyline

Status of Projects August 2024 – Cyprus High School

August 2024

Updates:

Site Work:
●Football field turf and running track
●Concrete walkways on the east side of the Baseball/Softball field
●Baseball field grading, infill, and fencing
●Roll up doors on the home side bleacher storage

Athletics/Pool:
●Slab on grade pour in the Pool
●Jumbotron and scoreboard installation

Administration/Commons:
●Learning Stairs framed for concrete pour
●Curtain wall/glazing around the Commons
●Metal panels on levels 2 and 3 of Administration

Academics/CTE:
●Masonry walls in the Manufacturing Shop
●Lab cabinetry
●Tile in the group restrooms

Performing Arts:
●Lighting in the Auditorium
●Lights in the Black Box Theater

Recent Photos:

Football Field turf and Running Track
Football Field turf and Running Track
Concrete walkways east of Baseball/Softball Field
Concrete walkways east of Baseball/Softball Field
Baseball Field grading, infill, and fencing
Baseball Field grading, infill, and fencing
Roll up doors on home side bleacher storage
Roll up doors on home side bleacher storage
Slab on grade at the bottom of the Pool
Slab on grade at the bottom of the Pool
Jumbotron installation in Athletics
Jumbotron installation in Athletics
Learning Stairs framed for concrete pour
Learning Stairs framed for concrete pour
Curtain wall frame around the Commons
Curtain wall frame around the Commons
Metal panels on levels 2 and 3 of Administration
Metal panels on levels 2 and 3 of Administration
Masonry walls in the Manufacturing Shop
Masonry walls in the Manufacturing Shop
Case work in the Physics Lab
Case work in the Physics Lab
Tile in group restrooms
Tile in group restrooms
Lighting in the Auditorium
Lighting in the Auditorium
Lights in the Black Box Theater
Lights in the Black Box Theater

Filed Under: Cyprus

West Lake Construction Update – June 2024

June 2024

Filed Under: Project Updates, West Lake

Status of Projects Update: June 2024

June 2024

Watch the presentation in the video below for updates about Granite School District construction projects. This presentation was given in the June 2024 Board of Education Meeting – Administrative Session. June 2024 Board of Education Capitol and Construction Update Slide Presentation.

Filed Under: Project Updates

Status of Projects June 2024 – Cyprus High School

June 2024

Updates:

Site Work:
● Stadium field base
● Stadium field fencing
● Stadium field drainage
● Flatwork behind home bleachers

Athletics/Pool:
● Track glass handrail
● Precast concrete benches in team locker rooms
● Pool plumbing

Administration/Commons:
● Framing in Administration
● Curtain wall/glazing around the Commons
● Testing Center siding

Academics/CTE:
● Finish paint, casework, and ceiling in Level 3 Academics
● Ceiling grid Levels 2 and 3 Academics
● Underground plumbing/electrical Manufacturing Shop

Performing Arts:
● Auditorium clouds finished

Recent Photos:

Stadium field base and perimeter fencing
Stadium field base and perimeter fencing
Stadium field drainage and curbing
Stadium field drainage and curbing
Flatwork behind the home team bleachers
Flatwork behind the home team bleachers
Glass handrail in Athletics
Glass handrail in Athletics
Pre-cast benches in team locker rooms
Pre-cast benches in team locker rooms
In-ground plumbing progress in the Pool
In-ground plumbing progress in the Pool
Framing in Administration
Framing in Administration
Glass glazing and frames outside Commons Area
Glass glazing and frames outside Commons Area
Testing Center siding
Testing Center siding
Casework, ceiling grid, and paint in Academics
Casework, ceiling grid, and paint in Academics

Filed Under: Cyprus

Status of Projects June 2024 – Skyline High School

June 2024

Updates:

Academics

● LVT flooring nearing completion on the Main Level
● Pre-cast stairs installed on Main Staircase
● Site concrete in Courtyard being poured
● Student/teacher furniture being delivered and installed
● Ceiling tile dropped in all corridors
● Tile nearing completion throughout building
● All teacher material has been removed from the old Academics building and is being stored/moved   into the new building
● Abatement of old building started June 3rd
● Casework nearing completion throughout all classrooms
● Manufacturing lab equipment being set
● Kitchen equipment installed

Recent Pictures:

View of Academics from Central Courtyard
View of Academics from Central Courtyard
Furniture installation in Administration
Furniture installation in Administration
Furniture installed in Career Center
Furniture installed in Career Center
Classroom with student desks installed
Classroom with student desks installed
Large format tile installation in Serving Area
Large format tile installation in Serving Area
LVT flooring installation in the
Commons Area
LVT flooring installation in the
Commons Area
Men’s restroom on Level 2
Men’s restroom on Level 2
Pre-cast stairs installed on the
Learning Staircase
Pre-cast stairs installed on the
Learning Staircase
Science classroom with rubber
flooring installed
Science classroom with rubber
flooring installed
LVT flooring installed in Main L2 Corridor
LVT flooring installed in Main L2 Corridor
Temporary pathway around the old
Auditorium placed
Temporary pathway around the old
Auditorium placed
Circular seating placed in Central Courtyard
Circular seating placed in Central Courtyard
Manufacturing Lab with equipment being set
Manufacturing Lab with equipment being set
Wood accent wall installation in Level 2
Commons Space
Wood accent wall installation in Level 2
Commons Space

Filed Under: Skyline

Status of Projects June 2024 – West Lake STEM

June 2024

Updates:

  • Grading, landscaping, irrigation piping, and site concrete installation continues.
  • Exterior finishes are approximately 90% complete.
  • Interior finishes in the Science and Academic Wings are 75% complete.
  • Interior finishes in the Auditorium and CTE Wings are 50% complete.
Lockers installed in hallways
Lockers installed in hallways
Lockers installed in Athletic locker rooms
Lockers installed in Athletic locker rooms
Exterior finishes
Exterior finishes
Exterior finishes
Exterior finishes
Stage rigging installation in progress
Stage rigging installation in progress
Collaboration space ceiling treatment
installed
Collaboration space ceiling treatment
installed
Gym flooring acclimatizing prior to installation
Gym flooring acclimatizing prior to installation
Landscaping and irrigation in progress
Landscaping and irrigation in progress
Restroom doors being installed
Restroom doors being installed
Balcony guardrail glass being installed
Balcony guardrail glass being installed
Carpet, cabinetry, and wall finishes in Academic Wing
Carpet, cabinetry, and wall finishes in Academic Wing
Carpet, cabinetry, and wall finishes in Academic Wing
Carpet, cabinetry, and wall finishes in Academic Wing

Filed Under: West Lake

  • « Go to Previous Page
  • Page 1
  • Page 2
  • Page 3
  • Page 4
  • Interim pages omitted …
  • Page 18
  • Go to Next Page »

Primary Sidebar

Website Search

  • Home
  • 2017 Bond Info
    • Plan of Finance and Progress Report
    • Phase One Update
    • Why Rebuild?
      • Facility Conditions
      • 21st Century Learning
      • Safety & Security
    • Research & Design
      • Design FAQ
      • Examples
      • Imperatives
  • Contact

Current Projects

  • Cyprus High School
    • Project Updates
    • Layout
  • Skyline High School
    • Project Updates
    • Layout
    • Timeline
  • West Lake Jr. High
    • Project Updates
    • Layout & Timeline
  • All Updates


Non-Discrimination Statement

Granite School District prohibits discrimination, harassment (including sexual harassment), or retaliation on the basis of race, color, sex, pregnancy, religion, national origin, marital status, disability, sexual orientation, gender identity or any other legally protected classification in all educational programs, activities, admissions, access, treatment, or employment practices and provides equal access to scouting groups and other designated youth groups. Related inquiries and complaints may be directed to a school administrator or to David Gomez, Title IX Coordinator, 504 Coordinator, and Director of Educational Equity, (385) 646-5000. You may also contact the Office for Civil Rights, Denver, CO, (303) 844-5695. Read Policy V.C.1.

Commitment to Accessibility

The Granite School District is committed to making our content accessible to all members of the public and district, including those with disabilities. If this applies to you, and you would like to provide feedback or report a concern, please contact our Communications Office.

Content Disclaimer

The Granite School District is not responsible for the text and content of websites not owned and operated by the Granite School District.

© 2025 Granite School District

 

Loading Comments...