Objective
Update the GSD Board and Superintendency on the progress of major construction projects overseen by the Architecture, Engineering & Construction Department on behalf of Granite School District.
Security Upgrades
Hartvigsen Security Remodel
Demolition is complete.
Installation of secure entry storefront is scheduled for mid July.
Project is scheduled to finish early August.


Rolling Meadows Security Remodel
Demolition is complete.
Awaiting materials to begin construction.
Project is scheduled to finish early August.


William Penn Security Remodel
Contract has been awarded.
Will mobilize beginning of July.
Construction Remodels
GEC Cafe Dish Room Remodel
Demolition complete.
Bringing in new dishwasher.
Preparing to install new flooring and wall paneling.
Estimated completion by end of August.


GTI 3rd Floor Pharmacy/Animation
Demolition is complete in the pharmacy lab.
Pharmacy lab framing is underway, and casework is in production.
Demolition is complete in the animation lab.
The animation lab electrical has been placed and drywall hung.
Painting for animation lab will occur in July.
Pharmacy Lab

Animation Lab


Granger High School Football Field Turf Replacement
Excavation of irrigation trench around field is complete.
Irrigation pipe is installed and backfilling is in progress.
Field graphic design finalized.




Taylorsville High School Football Field Water Cannon Cool Down System
Excavation of irrigation trench around field is complete.
Irrigation pipe is installed and backfilling is in progress.


Cottonwood High School Auditorium Sound System
Granite Maintenance department finished demolition.
New sound booth is being constructed.
New electrical panel has been installed.


New Construction
West Lake STEM Junior High School Building Construction
Perimeter footings and foundations are 75% complete.
Approximately 20,000 sq. ft. of slab has been placed.





- West Lake High School Cost Summary
- Demolition Fees – PO #270183
- Demolition Payments to Date: $1,251,749.00
- Staff Level Change Orders: $12,903.00
- Change Order Sub Total: $12,903.00
- Construction Fees – PO #270409
- Construction Payments to Date: $7,568,863.21
- Change Orders Requiring Board Authorization Owner Request
- Advancing Work Into Earlier Phase
- Unknown Conditions: $196,074.43
- Errors & Omission
- Staff Level Change Orders
- Change Order Sub Total: $196,074.43
- Phase Advancement Sub Total: $0.00
- Bid Price: $56,934,400.00
- Revised Cost: $57,130,474.43
- Summary
- Payments to Date – Grand Total: $8,820,612.21
- Change Order – Grand Total: $208977.43
- Phase Advancement – Grand Total: $0.00
- Demolition Fees – PO #270183
Skyline High School Athletics Complex & Academics Building
Fencing continues at North property line.
Softball grading is almost complete.
Water main tie ins at Softball are complete.
MEP ongoing.
Main gymnasium wood floor is beginning to be sanded.
Auxiliary gym wood floor is being set. Interior corridor flooring ongoing.
Mechanical startups have commenced.
Abatement at old Aux Gym/Pool building complete.
Existing pool demo to start in July.






- Skyline High School Cost Summary
- Construction Management Fees PO #070055
- Construction Payments to Date: #5,894,216.70
- Change Orders Requiring Board Authorization Owner Request: $5,827,842.00
- Change Order Sub Total: $5,827,842.00
- Phase 1 – Baseball Field – PO #070441
- construction Payments to Date: $3,211,958.50
- Change Orders Requiring Board Authorization Advancing work Into Earlier Phase: $208,891.99
- Unknown Conditions: $60,139.64
- Staff Level Change Orders: -$266,179.97
- Change Order Sub Total: $2,851.66
- Phase Advancement Sub Total: $208,891.99
- Phase 2 – Athletics – PO #170038
- Construction Payments to Date: $37,829,647.29
- Change Orders Requiring Board Authorization Owner Request: $2,513,634.43
- Advancing Work Into Earlier Phase: $654,253.71
- Unknown Conditions: $107,237.02
- Errors & Omission: $305,449.44
- Staff Level Change Orders: -$2,655,776.96
- Change Order Sub Total: $924,797.64
- Phase Advancement Sub Total: $654,253.71
- Phase 3 – Site Package – PO #270113
- Construction Payments to Date: $7,039,881.38
- Change Orders Requiring Board Authorization Owner Request: $0.00
- Advancing Work Into Earlier Phase: $193,225.74
- Unknown Conditions: $71,537.66
- Errors & Omission: $48,139.45
- Staff Level Change Orders: -$1,590,104.04
- Change Order Sub Total: -$1,277,201.19
- Phase Advancement Sub Total: $193,225.74
- Phase 4 – Academic Building – PO #270306
- Construction Payments to Date: $7,275,999.49
- Change Orders Requiring Board Authorization Own Request
- Advancing Work Into Earlier Phase
- Unknown Conditions: $1,010.00
- Errors & Omission: $59,089.87
- Staff Level Change Orders: -$2,178,892.05
- Change Order Sub Total: -$2,118,792.18
- Phase Advancement Sub Total
- Summary
- Payments to Date – Grand Total: $61,251,703.36
- Change Order – Grand Total: $3,359,497.93
- Phase Advancement – Grand Total: $1,056,371.44
- Bid Price approved by board 11/2021: $173,736,642.48
- Revised Coast: $174,262,478.61
- Construction Management Fees PO #070055
Cyprus High School Building Construction
More gymnasium tilt panels have been formed and poured
Pool foundation walls have been poured. Others are being formed
Auditorium foundation radius wall and orchestra pit back wall have been poured
Kitchen main underground electrical being installed for transformers and generators.
All crane paths have been installed.





- Cyprus High School Cost Summary
- Phase 1 Mass Grading – PO #170253
- Construction Payments: $4,170,965.69
- Change Orders Requiring Board Authorization Owner Request: $167,624.60
- Staff Level Change Orders: $116,091.09
- Change Order Sub Total: $283,715.69
- Phase 2 Construction – PO #270185
- Construction Payments to Date: $27,789,131.57
- Change Orders Requiring Board Authorization Owner Request: $117,489.00
- Advancing Work Into Earlier Phase: $0.00
- Unknown Conditions: $97,742.76
- Errors & Omission: $287,643.70
- Staff Level Change Orders: $38,392.72
- Change Order Sub Total: $541,268.18
- Summary
- Payments to Date – Grand Total: $31,960,097.26
- Change Order – Grand Total: $824,983.87
- Bid Price: $170,224,520.30
- Revised Cost: $170,508,235.99
- Phase 1 Mass Grading – PO #170253
Artificial Turf Fields Condition Testing & Maintenance Recommendations 2022
Independent Field Testing
- GSD wanted to understand field conditions from independent and unbiased professionals
- GSD solicited for an independent artificial turf field testing consultant
- FireFly was chosen in 1Q 2022
- Firefly does not install fields
- Firefly is a national company fully certified to inspect fields for K 12, College, and professional users
- Firefly visited each location and conducted comprehensive testing in 2Q 2022
Testing
- FireFly conducted testing spring of 2022
- Most GSD fields are in reasonable condition or able to have maintenance improve their condition
- 1 field was determined to have only 1 or 2 seasons of play left (Granger)
- Wear was so significant that maintenance would only be able to add minimal levels of fill materials
- Expectations have changed since grass fields
- The expectation if to have softer and more aesthetically pleasing fields into the future
- More days of play
- GSD fields will be safe
- GSD fields are in above average condition for their age
- Only new fields (0 3 years old) will get very high marks
- GSD maintenance will work over the summer to completed recommended maintenance
- GSD will re test in the fall of 2022 to check the efficacy of summer maintenance
Tests Conducted
Test Type | Test Method | Test Description |
HIC | EN 117:2008 | Impact Attenuating Playground Surfacing – Determination of Critial Fall Height |
G-Max | ASTM F1936-19 | Standard Specification for Impact Attenuation of Turf Playing Systems as Measured in the Field |
Infill Depths | EN 1969:2000 | Surfaces for Sports Areas – Determination of Thickness of Synthetic Sports Surfaces |
AAA | ASTM F3189-20 | Standard Test Method for Measuring Force Reduction, Vertical Deformation, and Energy Restitution of Synthetic Turf Systems Using the Advanced Artificial Athlete |
Vertical Ball Rebound | BS EN 12235:2013 | Surfaces for Sports Areas – Determination of Vertical Ball Behavior |
Ball Roll | EN 12234:2013 | Surfaces for Sports Areas – Determination of Ball Roll Behavior |
Rational Resistance | EN 15301-1:2007 | Surfaces for Sports Areas – Part 1: Determination of Rotational Resistance |
Planarity | EN 13036-7:2003 | Road and Airfield Surface Characteristics – Irregularity Measurement of Pavement Courses – The Straightedge Test |
Test Locations

Maintenance
- We have field specific maintenance recommendations
- Most field issues can be solved with summer maintenance
- GSD has been asked to perform a scarification process with a tined rake
- We have not done that procedure before
- This should have significant positive impact on the preparation of the play surface
- It loosens up compacted materials
- Stands up fibers
- Standing fibers allow for more infill to be placed
- Infill will be placed after scarification
- Increased infill remediates most negative play and safety considerations as measured this spring
Cottonwood

Project Scope
Proposed Remediation ( in Order)
- Repair all open seams
- Perform Maintenance using drag brush/tines to scarify surface and by first facing fibers all in one direction, followed by the same procedure in opposing direction. The goal of this will be to stand fibers in preparation for additional infill.
- Add infill to carpet capacity in areas of high wear. In isolated areas (goal mouths) if sufficient infill cannot be achieved, a replacement patch should be installed.
- Check infill depth consistency and repeat as necessary until proper infill depths are achieved.
Long Term Maintenance
- Repeat as needed, per manufacturer’s recommendations
- Perform maintenance prior to annual g-max testing
- Rotate drag brush annually to prevent directional sag.
Cyprus

Project Scope
Proposed Remediation ( in Order)
- Repair all open seams
- Perform Maintenance using drag brush/tines to scarify surface and by first facing fibers all in one direction, followed by the same procedure in opposing direction. The goal of this will be to stand fibers in preparation for additional infill.
- Add infill to carpet capacity in areas of high wear. In isolated areas (goal mouths) if sufficient infill cannot be achieved, a replacement patch should be installed.
- Check infill depth consistency and repeat as necessary until proper infill depths are achieved.
Long Term Maintenance
- Repeat as needed, per manufacturer’s recommendations
- Perform maintenance prior to annual g-max testing
- Rotate drag brush annually to prevent directional sag.
Kearns

Project Scope
Proposed Remediation ( in Order)
- Repair all open seams
- Perform Maintenance using drag brush/tines to scarify surface and by first facing fibers all in one direction, followed by the same procedure in opposing direction. The goal of this will be to stand fibers in preparation for additional infill.
- Add infill to carpet capacity in areas of high wear. In isolated areas (goal mouths) if sufficient infill cannot be achieved, a replacement patch should be installed.
- Check infill depth consistency and repeat as necessary until proper infill depths are achieved.
Long Term Maintenance
- Repeat as needed, per manufacturer’s recommendations
- Perform maintenance prior to annual g-max testing
- Rotate drag brush annually to prevent directional sag.
Hunter

Project Scope
Proposed Remediation ( in Order)
- Repair all open seams
- Perform Maintenance using drag brush/tines to scarify surface and by first facing fibers all in one direction, followed by the same procedure in opposing direction. The goal of this will be to stand fibers in preparation for additional infill.
- Add infill to carpet capacity in areas of high wear. In isolated areas (goal mouths) if sufficient infill cannot be achieved, a replacement patch should be installed.
- Check infill depth consistency and repeat as necessary until proper infill depths are achieved.
Long Term Maintenance
- Repeat as needed, per manufacturer’s recommendations
- Perform maintenance prior to annual g-max testing
- Rotate drag brush annually to prevent directional sag.
Olympus

Project Scope
Proposed Remediation ( in Order)
- Repair all open seams
- Perform Maintenance using drag brush/tines to scarify surface and by first facing fibers all in one direction, followed by the same procedure in opposing direction. The goal of this will be to stand fibers in preparation for additional infill.
- Add infill to carpet capacity in areas of high wear. In isolated areas (goal mouths) if sufficient infill cannot be achieved, a replacement patch should be installed.
- Check infill depth consistency and repeat as necessary until proper infill depths are achieved.
Long Term Maintenance
- Repeat as needed, per manufacturer’s recommendations
- Perform maintenance prior to annual g-max testing
- Rotate drag brush annually to prevent directional sag.
Taylorsville
