Status of Projects
May 2022
Architecture, Engineering & Construction

May, 2022 by Granite Schools

Objective

Update the GSD Board and Superintendency on the progress of major construction projects overseen by the Architecture, Engineering & Construction Department on behalf of Granite School District.

Security Upgrades

Security Upgrades/Remodels
Security Upgrades/Remodels

Hartvigsen Security Remodel – No Change Since Last Month

Project awarded to Old Granite Innovations Construction.
Pre-construction meeting completed.
Contractor has submitted and architect is reviewing shop drawings.

Rolling Meadows Security Remodel – No Change Since Last Month

Project awarded to Wasatch West Contracting.
Pre-construction meeting completed.
Contractor has submitted and architect is reviewing shop drawings.

New Construction

West Lake STEM Junior High School Building Construction

40% of excavation for footings has been completed.
Footings and foundation walls are in progress.
Storm water drainage system has begun.

Front office footing excavation
Front office footing excavation
Forming of south-east classroom wing foundation walls
Forming of south-east classroom wing foundation walls
Backfill and insulation of foundation wall
Backfill and insulation of foundation wall
Mat slab footings
Mat slab footings
East classroom wing mat footing
East classroom wing mat footing
East classroom wing footings
East classroom wing footings
  • West Lake High School Cost Summary
    • Demolition Fees: PO #270183
      • Demolition Payments to Date: $1,251,749.00
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing work into earlier phase
      • Unknown Conditions
      • Errors & Omission
      • Staff Level Change Orders: $12,903.00
      • Change Order Sub Total: $12,903.00
    • Construction Fees: PO #270409
      • Construction Payments to Date: $2,893,697.15
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing work into earlier phase
      • Unknown Conditions: $196,074.43
      • Errors & Omission
      • Stagg Level Change Orders
      • Change Order Sub Total: $196,074.43
      • Phase Advancement Sub Total: $0.00
    • Summary
      • Payments to Date – Grand Total: $4,145,446.15
      • Change Order – Grand Total: $208,977.43
      • Phase Advancement – Grand Total: $0.00
      • Bid Price: $56,934,400.00
      • Revised Cost: $57,130,474.43
      • Owner Costs Budget: $11,482,700.00
      • Design, demo, FFE, infrastructure, special testing insurance: $61,105,817.43
  • West Lake High School Cost Summary
    • Demolition Fees: PO #270183
      • Demolition Payments to Date: $1,251,749.00
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing work into earlier phase
      • Unknown Conditions
      • Errors & Omission
      • Staff Level Change Orders: $12,903.00
      • Change Order Sub Total: $12,903.00
    • Construction Fees: PO #270409
      • Construction Payments to Date: $2,893,697.15
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing work into earlier phase
      • Unknown Conditions: $196,074.43
      • Errors & Omission
      • Stagg Level Change Orders
      • Change Order Sub Total: $196,074.43
      • Phase Advancement Sub Total: $0.00
    • Summary
      • Payments to Date – Grand Total: $4,145,446.15
      • Change Order – Grand Total: $208,977.43
      • Phase Advancement – Grand Total: $0.00
      • Bid Price: $56,934,400.00
      • Revised Cost: $57,130,474.43
      • Owner Costs Budget: $11,482,700.00
      • Design, demo, FFE, infrastructure, special testing insurance: $61,105,817.43

Skyline High School Athletics Complex & Academics Building

Field Turf has commenced work on the synthetic turf field.
Forming walls at the Millcreek pedestrian staircase.
MEP finish work ongoing.
Main entrance storefront and doors installed.
Flooring has commenced in locker rooms, weight room, gymnasium,and dance room.
Site work continues at the playing fields.
Fencing continues at the west and north fence lines.
Pool has been drained, cleaned, and refilled. Pool deck is complete.
Training and commissioning of the pool scheduled for May.
Mechanical room work ongoing.

Skyline Campus

Skyline overview looking northeast
Skyline overview looking northeast
Skyline overview looking northwest
Skyline overview looking northwest
Floor being prepped in gym
Floor being prepped in gym
Team locker rooms
Team locker rooms
Dance room
Dance room
Weight room
Weight room
North fencing next to turf field
North fencing next to turf field
Turf field drainage
Turf field drainage
North property line looking west
North property line looking west
North property line looking east
North property line looking east
North property line utilities
North property line utilities
West property line retaining wall
West property line retaining wall
Millcreek stair
Millcreek stair
  • Skyline High School Cost Summary
    • Construction Management Fees: PO #070055
      • Construction Payments to Date: $5,496,125.52
      • Change Orders Requiring Board Authorization Owner Request: $5,827,842.00
      • Change Order Sub Total: $5,827,842.00
    • Phase 1 – Baseball Field: PO #070441
      • Construction Payments to Date: #3,211,958.50
      • Change Orders Requiring Board Authorization Owner Request: $208,891.99
      • Unknown Conditions: $60,139.64
      • Staff Level Change Orders: -$266,179.97
      • Change Order Sub Total: $2,851.66
      • Phase Advancement Sub Total: $208,891.99
    • Phase 2 – Athletics: PO #170038
      • Construction Payments to Date: $36,193,221.18
      • Change Orders Requiring Board Authorization Owner Request: $2,513,634.43
      • Advancing work into earlier phase: $654,253.71
      • Unknown Conditions: $107,237.02
      • Errors & Omission: $282,351.94
      • Staff Level Change Orders: -$2,654,352.06
      • Change Order Sub Total: $903,125.04
      • Phase Advancement Sub Total: $654,253.71
    • Phase 3 – Site Package: PO #270113
      • Construction Payments to Date: $4,562,207.21
      • Change Orders Requiring Board Authorization Owner Request: $0.00
      • Advancing work into earlier phase: $193,225.74
      • Unknown Conditions: $70,910.42
      • Errors & Omission: $48,139.45
      • Staff Level Change Orders: -$1,590,104.04
        • CO5 Retaining wall, gates, comcast, AED cabinets: -$9,276.25
      • Change Order Sub Total: -$1,277,828.43
      • Phase Advancement Sub Total: $193,225.74
    • Phase 4 – Academic Building: PO #270306
      • Construction Payments to Date: $4,581,940.66
      • Change Orders Requiring Board Authorization Owner Request
      • Advancing work into earlier phase
      • Unknown Conditions
      • Errors & Omission: $59,089.87
      • Staff Level Change Orders: -$2,178,071.00
      • Change Order Sub Total: -$2,118,981.13
      • Phase Advancement Sub Total
    • Summary
      • Payments to Date – Grand Total: $54,045,453.07
      • Change Order – Grand Total: $3,337,009.14
      • Phase Advancement – Grand Total: $1,056,371.44
      • Bid Price approved by board 11/2021: $173,736,642.48
      • Revised Cost: $174,251,352.39
      • Owner Costs Budget: $21,013,220.00
      • Design, demo, construction management, temporary buildings, FFE, infrastructure, special testing, insurance: $10,445,227.35

Cyprus High School Building Construction

Athletics slab on grade has been poured for team locker rooms, wrestling room, coach’s offices, along with PE locker rooms.
Forming tilt-up walls. Setting rebar and electrical conduit and other embedded items.
Crane is on site, being assembled and crane paths have been installed.
Pool footings have been installed. Pool has been excavated and filled in with structural fill and made into a crane path for tilt panels.
Foundation walls being poured between pool and commons.
GeoEnergy drilling continues. 75 out of 200 holes drilled.
Academics footings have been installed.
Underground electrical being installed in orchestra area.
Underground plumbing is continuing in kitchen.
Retaining walls currently being installed along Cordero Drive are waiting on design from contractor.

Casting slabs, framing tilt walls, and crane paths
Casting slabs, framing tilt walls, and crane paths
Crane onsite being built
Crane onsite being built
View of site crane paths
View of site crane paths
Foundation walls and columns being formed up in pool area
Foundation walls and columns being formed up in pool area
Orchestra pit underground electrical
Orchestra pit underground electrical
Auto shop footings, hillside drainage finished
Auto shop footings, hillside drainage finished
  • Cyprus High School Cost Summary
    • Phase 1 Mass Grading: PO #170253
      • Construction Payments: $4,170,965.69
      • Change Orders Requiring Board Authorization Owner Request: $167,624.60
      • Staff Level Change Orders: $283,715.69
    • Phase 2 Construction: PO #270185
      • Construction Payments to Date: $16,896,903.85
      • Change Orders Requiring Board uthorization Owner Request: $117,489.00
      • Unknown Conditions: $97,742.76
      • Errors & Omission: $287,643.70
      • Staff Level Change Orders: $60,788.47
      • Change Order Sub Total: $563,663.93
    • Summary
      • Payments to Date – Grand Total: $21,067,869.54
      • Change order – Grand Total: $847,379.62
      • Bad Price: $170,224,520.30
      • Revised Cost: $170,508,235.99

Ratification – Summer Purchases

  • Summer construction is the busiet time for the maintenance and AEC departments.
  • All purchases go through the proper purchasing department channels.
  • Past Practice on significant purchases over $50,000 get approval from the Superintendent.
  • Often purchases need to be made to support “summer” projects.
    • Summer projects have less then 10 week to complete
  • Often lead times drive the timing or purchases.
    • Lead time delays can require quick responses.
  • Purchase can be needed to support school growth needs such as:
    • Classroom furniture
    • Teching technology
  • HVAC systems will often break during summer months and the need to repair prior to the start of school is paramount
  • The Maintenance department will, on occasion, need to purchase materials as unknown conditions unveil themselves and may require purchases of material, etc.